Which of the following describes crashing a project schedule?
The correct answer is B. Additional resources are deployed. See the full explanation below for the reasoning.
Question
Which of the following describes crashing a project schedule?
Options
- AProject activities that would normally be completed in sequence are performed concurrently.
- BAdditional resources are deployed.
- CAll float time is removed from the project schedule.
- DThe project manager reviews the project scope to determine unnecessary requirements.
How the community answered
(61 responses)- A2% (1)
- B82% (50)
- C11% (7)
- D5% (3)