Which of the following describes crashing a project schedule?

The correct answer is B. Additional resources are deployed. See the full explanation below for the reasoning.

Question

Which of the following describes crashing a project schedule?

Options

  • AProject activities that would normally be completed in sequence are performed concurrently.
  • BAdditional resources are deployed.
  • CAll float time is removed from the project schedule.
  • DThe project manager reviews the project scope to determine unnecessary requirements.

How the community answered

(61 responses)
  • A
    2% (1)
  • B
    82% (50)
  • C
    11% (7)
  • D
    5% (3)