A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following…

The correct answer is B. Precedence Diagramming Method (PDM). See the full explanation below for the reasoning.

Question

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

Options

  • AArrow Diagramming Method (ADM)
  • BPrecedence Diagramming Method (PDM)
  • CCritical Path Method (CPM)
  • DCritical Chain Method (CCM)