A project manager is recording the probability and impact of an uncertain event. Which of the following would be the BEST document to capture this data?

The correct answer is C. Risk register. See the full explanation below for the reasoning.

Question

A project manager is recording the probability and impact of an uncertain event. Which of the following would be the BEST document to capture this data?

Options

  • AIssues log
  • BResponsibility assignment matrix
  • CRisk register
  • DActivity log

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    11% (4)
  • C
    84% (32)
  • D
    3% (1)