During the weekly status meeting, it is determined the project will take two months longer to complete. The customer asks the project manager to modify the original end date to the new project end…
The correct answer is D. Change request form. See the full explanation below for the reasoning.
Question
During the weekly status meeting, it is determined the project will take two months longer to complete. The customer asks the project manager to modify the original end date to the new project end date. Which of the following documents should be completed FIRST?
Options
- AProject schedule
- BProject management plan
- CStatement of Work (SOW)
- DChange request form
How the community answered
(33 responses)- A12% (4)
- B3% (1)
- C9% (3)
- D76% (25)