JK0-017 · Question #13
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
The correct answer is A. Transition plan. See the full explanation below for the reasoning.
Question
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
Options
- ATransition plan
- BQuality plan
- CChange Control plan
- DProcurement plan
How the community answered
(19 responses)- A74% (14)
- B16% (3)
- C5% (1)
- D5% (1)