Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?
The correct answer is B. Activity A must end before Activity B can begin. See the full explanation below for the reasoning.
Question
Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?
Options
- AActivity A must end before Activity B can end.
- BActivity A must end before Activity B can begin.
- CActivity A must begin before Activity B can begin.
- DActivity A must begin before Activity B can end.
How the community answered
(28 responses)- A7% (2)
- B79% (22)
- C4% (1)
- D11% (3)