JK0-017 · Question #54

Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?

The correct answer is B. Activity A must end before Activity B can begin. See the full explanation below for the reasoning.

Question

Which of the following is indicative of a `finish-to-start' direct relationship in a project schedule?

Options

  • AActivity A must end before Activity B can end.
  • BActivity A must end before Activity B can begin.
  • CActivity A must begin before Activity B can begin.
  • DActivity A must begin before Activity B can end.

How the community answered

(28 responses)
  • A
    7% (2)
  • B
    79% (22)
  • C
    4% (1)
  • D
    11% (3)