During the project management process, an organization develops a document that details preferred and authorized interactions among project team members, senior management, and other project…

The correct answer is C. Communications management plan. See the full explanation below for the reasoning.

Question

During the project management process, an organization develops a document that details preferred and authorized interactions among project team members, senior management, and other project stakeholders. Which of the following types of documents were developed?

Options

  • AQuality management plan
  • BChange control plan
  • CCommunications management plan
  • DRisk management plan

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    83% (19)
  • D
    9% (2)