JK0-017 · Question #53
Which of the following is crucial to scope management?
The correct answer is D. A formal change management process. See the full explanation below for the reasoning.
Question
Which of the following is crucial to scope management?
Options
- AA Work Breakdown Structure dictionary
- BA final statement of project objectives
- CAn automated scope management system
- DA formal change management process
How the community answered
(27 responses)- A11% (3)
- B4% (1)
- C4% (1)
- D81% (22)