nerdexam
CompTIA

JK0-017 · Question #495

In order to satisfy a difficult stakeholder, a project manager has asked the project team to include more services than were outlined in the statement of work (SOW). Which of the following will be…

The correct answer is C. It may increase the cost of the project. See the full explanation below for the reasoning.

Question

In order to satisfy a difficult stakeholder, a project manager has asked the project team to include more services than were outlined in the statement of work (SOW). Which of the following will be the MOST likely impact on the outcome of the project?

Options

  • AIt may decrease the scope of the project.
  • BIt may satisfy the project sponsor.
  • CIt may increase the cost of the project.
  • DIt may require the use of fewer resources.

How the community answered

(18 responses)
  • A
    11% (2)
  • B
    6% (1)
  • C
    78% (14)
  • D
    6% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice