A project manager has been asked to create an issues log. Which of the following should be included in the issues log? (Select TWO).

The correct answer is A. The description of the issue D. The date the issue was submitted. See the full explanation below for the reasoning.

Question

A project manager has been asked to create an issues log. Which of the following should be included in the issues log? (Select TWO).

Options

  • AThe description of the issue
  • BThe cost of the issue
  • CThe risk log
  • DThe date the issue was submitted
  • EThe work breakdown structure (WBS)

How the community answered

(42 responses)
  • A
    81% (34)
  • B
    5% (2)
  • C
    2% (1)
  • E
    12% (5)