The team members have notified the project manager of several risks which may have a significant impact upon the project. Which of the following should the project manager do FIRST to address these…
The correct answer is D. Manage the risks with the highest impact. See the full explanation below for the reasoning.
Question
The team members have notified the project manager of several risks which may have a significant impact upon the project. Which of the following should the project manager do FIRST to address these risks?
Options
- AManage the risks with the lowest impact.
- BRecommend the cancellation of the project.
- CIgnore the risks.
- DManage the risks with the highest impact.
How the community answered
(19 responses)- A11% (2)
- B5% (1)
- C16% (3)
- D68% (13)