Question

A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?

Options

  • ACommunications management plan
  • BCost management plan
  • CProject charter
  • DContract management plan