nerdexam
CompTIA

JK0-017 · Question #461

A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the…

The correct answer is A. Communications management plan. See the full explanation below for the reasoning.

Question

A project sponsor has requested that weekly status updates are to be sent by email, detailing the schedule performance index (SPI) and schedule variance (SV) of the project. In which of the following documents should these requirements be included?

Options

  • ACommunications management plan
  • BCost management plan
  • CProject charter
  • DContract management plan

How the community answered

(21 responses)
  • A
    71% (15)
  • B
    10% (2)
  • C
    5% (1)
  • D
    14% (3)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice