nerdexam
CompTIA

JK0-017 · Question #460

Which of the following are characteristics of a projects critical path? (Select Two).

The correct answer is A. The critical path is the longest duration. D. The critical path has less than or equal to zero float time. See the full explanation below for the reasoning.

Question

Which of the following are characteristics of a projects critical path? (Select Two).

Options

  • AThe critical path is the longest duration.
  • BThe critical path has the least amount of resources.
  • CThe critical path is the shortest duration.
  • DThe critical path has less than or equal to zero float time.
  • EThe critical path has a greater than zero float time.

How the community answered

(24 responses)
  • A
    71% (17)
  • B
    4% (1)
  • C
    8% (2)
  • E
    17% (4)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice