A key team member is performing poorly on a project. The project manager has verified that the team member knows the project expectations. The project manager has met repeatedly with this team member to outline expectations. Which of the following is the NEXT step the project manager should take to keep the project on schedule?
Options
- AIgnore the team members behavior.
- BTerminate the team member.
- CMove the team member to another project.
- DRequest the resource managers assistance.
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C12% (4)
- D79% (27)