A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only…
The correct answer is B. Requires planning and execution to be completed in parallel. See the full explanation below for the reasoning.
Question
A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?
Options
- AMinimizes risk due to decreased timeline.
- BRequires planning and execution to be completed in parallel.
- CMinimizes cost since work is completed in four months instead of six.
- DRequires rework due to decreased timeline.
How the community answered
(28 responses)- A4% (1)
- B75% (21)
- C14% (4)
- D7% (2)