A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only…

The correct answer is B. Requires planning and execution to be completed in parallel. See the full explanation below for the reasoning.

Question

A stakeholder has indicated that a three phase project must be completed in four months instead of the previously agreed upon six months. It is determined that fast-tracking the project is the only option. Which of the following is a characteristic of fast-tracking a project?

Options

  • AMinimizes risk due to decreased timeline.
  • BRequires planning and execution to be completed in parallel.
  • CMinimizes cost since work is completed in four months instead of six.
  • DRequires rework due to decreased timeline.

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    75% (21)
  • C
    14% (4)
  • D
    7% (2)