nerdexam
CompTIA

JK0-017 · Question #453

In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?

The correct answer is C. Benchmarking. See the full explanation below for the reasoning.

Question

In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?

Options

  • AProcess improvement
  • BQuality metrics
  • CBenchmarking
  • DCost-benefit analysis

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    7% (3)
  • C
    71% (29)
  • D
    17% (7)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice