CompTIA
JK0-017 · Question #453
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
The correct answer is C. Benchmarking. See the full explanation below for the reasoning.
Question
In order to compare a current projects quality to that of a previously completed project, a project manager should use which of the following techniques?
Options
- AProcess improvement
- BQuality metrics
- CBenchmarking
- DCost-benefit analysis
How the community answered
(41 responses)- A5% (2)
- B7% (3)
- C71% (29)
- D17% (7)
Community Discussion