CompTIA
JK0-017 · Question #455
The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?
The correct answer is D. The project costs are currently over-budget. See the full explanation below for the reasoning.
Question
The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?
Options
- AThe project costs are currently under-budget.
- BThe AC is less than the EV.
- CThe EV is higher than the AC.
- DThe project costs are currently over-budget.
How the community answered
(24 responses)- A8% (2)
- B17% (4)
- C4% (1)
- D71% (17)
Community Discussion
No community discussion yet for this question.