The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?

The correct answer is D. The project costs are currently over-budget. See the full explanation below for the reasoning.

Question

The EV of a particular project is $6 million. The CV is -$340,000. Which of the following can be determined from this information?

Options

  • AThe project costs are currently under-budget.
  • BThe AC is less than the EV.
  • CThe EV is higher than the AC.
  • DThe project costs are currently over-budget.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    17% (4)
  • C
    4% (1)
  • D
    71% (17)