Question

Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).

Options

  • AIt determines the project milestones.
  • BIt determines the project budget.
  • CIt outlines the communication plan for the team.
  • DIt determines the resources required to complete project tasks.
  • EIt outlines the statement of work (SOW) for the project.