Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).

The correct answer is B. It determines the project budget. D. It determines the resources required to complete project tasks. See the full explanation below for the reasoning.

Question

Which of the following are the benefits of a work breakdown structure (WBS)? (Select Two).

Options

  • AIt determines the project milestones.
  • BIt determines the project budget.
  • CIt outlines the communication plan for the team.
  • DIt determines the resources required to complete project tasks.
  • EIt outlines the statement of work (SOW) for the project.

How the community answered

(58 responses)
  • A
    5% (3)
  • B
    83% (48)
  • C
    2% (1)
  • E
    10% (6)

Community Discussion

No community discussion yet for this question.