If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

The correct answer is A. -$1,000. See the full explanation below for the reasoning.

Question

If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?

Options

  • A-$1,000
  • B$1,000
  • C-$3,000
  • D$3,000
  • EThere would be a 25 percent cost decrease.
  • FThere would be a 75 percent cost increase.
  • GThe project is over-budget.
  • HThe project is under-budget.