JK0-017 · Question #448
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
The correct answer is A. -$1,000. See the full explanation below for the reasoning.
Question
If the EV is $3,000 and the AC is $4,000, which of the following is the CV for the project?
Options
- A-$1,000
- B$1,000
- C-$3,000
- D$3,000
- EThere would be a 25 percent cost decrease.
- FThere would be a 75 percent cost increase.
- GThe project is over-budget.
- HThe project is under-budget.