Which of the following would be the impact upon a project if the CPI for the project is .75?
The correct answer is D. The project is over-budget. See the full explanation below for the reasoning.
Question
Which of the following would be the impact upon a project if the CPI for the project is .75?
Options
- AThe project is under-budget.
- BThere would be a 25 percent cost decrease.
- CThere would be a 75 percent cost increase.
- DThe project is over-budget.
How the community answered
(45 responses)- A4% (2)
- B11% (5)
- C7% (3)
- D78% (35)