Which of the following would be the impact upon a project if the CPI for the project is .75?

The correct answer is D. The project is over-budget. See the full explanation below for the reasoning.

Question

Which of the following would be the impact upon a project if the CPI for the project is .75?

Options

  • AThe project is under-budget.
  • BThere would be a 25 percent cost decrease.
  • CThere would be a 75 percent cost increase.
  • DThe project is over-budget.

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    11% (5)
  • C
    7% (3)
  • D
    78% (35)