If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
The correct answer is B. .75. See the full explanation below for the reasoning.
Question
If the EV is $3,000 and the AC is $4,000, which of the following would be the CPI for the project?
Options
- A.50
- B.75
- C1.25
- D1.75
How the community answered
(28 responses)- A11% (3)
- B71% (20)
- C4% (1)
- D14% (4)