When a project ends unexpectedly, which of the following should the project manager do?
The correct answer is C. Perform project close out with full documentation and review. See the full explanation below for the reasoning.
Question
When a project ends unexpectedly, which of the following should the project manager do?
Options
- ACreate an end document to add to the file before moving on to another project.
- BCreate a document identifying the negative impact of the early project ending to give to the
- CPerform project close out with full documentation and review.
- DPerform a limited project close that consists of releasing team members.
How the community answered
(45 responses)- A7% (3)
- B2% (1)
- C78% (35)
- D13% (6)