JK0-017 · Question #440
A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project…
The correct answer is B. Quality will be impacted. See the full explanation below for the reasoning.
Question
A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time. Which of the following will be impacted?
Options
- AProject scope will be impacted.
- BQuality will be impacted.
- CWBS will be impacted.
- DSOW will be impacted.
How the community answered
(43 responses)- A5% (2)
- B74% (32)
- C14% (6)
- D7% (3)