nerdexam
CompTIA

JK0-017 · Question #440

A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project…

The correct answer is B. Quality will be impacted. See the full explanation below for the reasoning.

Question

A project manager was called into the office of the Chief Information Officer (CIO) and informed that the resource budget for the company has been reduced by 10%. The CIO expects that the project must be completed on time. Which of the following will be impacted?

Options

  • AProject scope will be impacted.
  • BQuality will be impacted.
  • CWBS will be impacted.
  • DSOW will be impacted.

How the community answered

(43 responses)
  • A
    5% (2)
  • B
    74% (32)
  • C
    14% (6)
  • D
    7% (3)

Community Discussion

No community discussion yet for this question.