Which of the following can the project manager do to manage scope creep?

The correct answer is C. Be specific when defining project objectives in the project plan. See the full explanation below for the reasoning.

Question

Which of the following can the project manager do to manage scope creep?

Options

  • ABe open minded to new ideas to the project.
  • BBe flexible about what needs to be done to complete the project.
  • CBe specific when defining project objectives in the project plan.
  • DBe positive when approached with changes to ensure customer satisfaction.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    12% (3)
  • C
    81% (21)
  • D
    4% (1)