CompTIA
JK0-017 · Question #439
Which of the following should a project manger do to actively track issues as they are identified?
The correct answer is D. Update the issues log. See the full explanation below for the reasoning.
Question
Which of the following should a project manger do to actively track issues as they are identified?
Options
- ADevelop a quality management plan.
- BCreate a process for anonymous team review of issue resolution.
- CMake an issues log template.
- DUpdate the issues log.
How the community answered
(49 responses)- A6% (3)
- B2% (1)
- C10% (5)
- D82% (40)
Community Discussion
No community discussion yet for this question.