Quality assurance is performed during which phase of a project?

The correct answer is C. During the execution phase. See the full explanation below for the reasoning.

Question

Quality assurance is performed during which phase of a project?

Options

  • ADuring the controlling phase
  • BDuring both controlling and execution phase
  • CDuring the execution phase
  • DDuring the planning phase

How the community answered

(49 responses)
  • A
    14% (7)
  • B
    8% (4)
  • C
    73% (36)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.