Quality assurance is performed during which phase of a project?
The correct answer is C. During the execution phase. See the full explanation below for the reasoning.
Question
Quality assurance is performed during which phase of a project?
Options
- ADuring the controlling phase
- BDuring both controlling and execution phase
- CDuring the execution phase
- DDuring the planning phase
How the community answered
(49 responses)- A14% (7)
- B8% (4)
- C73% (36)
- D4% (2)