Question
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
Options
- AObtain additional approval from the project sponsor.
- BDiscuss this change during the next status meeting.
- CPerform a probability and impact analysis on the change.
- DCreate a plan to implement the change.