The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
The correct answer is D. Create a plan to implement the change. See the full explanation below for the reasoning.
Question
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
Options
- AObtain additional approval from the project sponsor.
- BDiscuss this change during the next status meeting.
- CPerform a probability and impact analysis on the change.
- DCreate a plan to implement the change.
How the community answered
(18 responses)- A11% (2)
- C6% (1)
- D83% (15)
Community Discussion