The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?

The correct answer is D. Create a plan to implement the change. See the full explanation below for the reasoning.

Question

The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?

Options

  • AObtain additional approval from the project sponsor.
  • BDiscuss this change during the next status meeting.
  • CPerform a probability and impact analysis on the change.
  • DCreate a plan to implement the change.

How the community answered

(18 responses)
  • A
    11% (2)
  • C
    6% (1)
  • D
    83% (15)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice