The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?
The correct answer is D. Perform an impact analysis. See the full explanation below for the reasoning.
Question
The project manager has documented a change request from a key project stakeholder. Which of the following actions should the project manager take NEXT?
Options
- ADiscuss this change during the next status meeting.
- BAsk other stakeholders for recommendations.
- CSend the request to the change control board.
- DPerform an impact analysis.
How the community answered
(44 responses)- A18% (8)
- B7% (3)
- C5% (2)
- D70% (31)