A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following…
The correct answer is D. Phase gate. See the full explanation below for the reasoning.
Question
A project manager has just completed the planning of a project, but cannot start the project execution until granted permission from the project sponsor. This is an example of which of the following actions?
Options
- AStakeholder analysis
- BRisk assessment
- CAudit review
- DPhase gate
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C4% (1)
- D81% (21)