Before the execution phase begins, who is in control of the project?

The correct answer is C. Project manager. See the full explanation below for the reasoning.

Question

Before the execution phase begins, who is in control of the project?

Options

  • AProject sponsor
  • BProgram manager
  • CProject manager
  • DProject coordinator

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    12% (3)
  • C
    76% (19)
  • D
    4% (1)