JK0-017 · Question #433
Which of the following would MOST likely contain warranty information for the project deliverable?
The correct answer is D. Transition plan. See the full explanation below for the reasoning.
Question
Which of the following would MOST likely contain warranty information for the project deliverable?
Options
- AScope statement
- BCost baseline
- CRisk assessment
- DTransition plan
How the community answered
(20 responses)- A5% (1)
- B10% (2)
- C5% (1)
- D80% (16)