JK0-017 · Question #40
Due to external market conditions, the Chief Executive Officer (CEO) has announced a company shift in strategic priorities. As such, more focus will be spent on tuning current operational…
The correct answer is D. Project cancellation. See the full explanation below for the reasoning.
Question
Due to external market conditions, the Chief Executive Officer (CEO) has announced a company shift in strategic priorities. As such, more focus will be spent on tuning current operational capabilities. Which of the following is the MOST likely outcome of an existing project that is currently in an initiation phase and about to enter stage-gate review and now falls outside of the new strategic priorities?
Options
- AStage extension
- BProject completion
- CStage completion
- DProject cancellation
How the community answered
(34 responses)- A3% (1)
- B6% (2)
- C15% (5)
- D76% (26)