Which of the following is included in the project charter?
The correct answer is B. Problem statement. See the full explanation below for the reasoning.
Question
Which of the following is included in the project charter?
Options
- AWork assignments
- BProblem statement
- CCost-benefit analysis
- DFeasibility assessments
How the community answered
(51 responses)- A20% (10)
- B71% (36)
- C6% (3)
- D4% (2)