CompTIA
JK0-017 · Question #399
During which of the following process groups is the preliminary project risk assessment performed?
The correct answer is B. Planning. See the full explanation below for the reasoning.
Question
During which of the following process groups is the preliminary project risk assessment performed?
Options
- AMonitoring/Controlling
- BPlanning
- CInitiating
- DExecuting
How the community answered
(43 responses)- A7% (3)
- B72% (31)
- C5% (2)
- D16% (7)
Community Discussion