Which of the following is a use for a Pareto diagram?

The correct answer is C. In quality management to identify and prioritize problem areas. See the full explanation below for the reasoning.

Question

Which of the following is a use for a Pareto diagram?

Options

  • AIn procurement management to evaluate vendor proposals.
  • BIn cost management to determine actual versus expected project costs.
  • CIn quality management to identify and prioritize problem areas.
  • DIn risk management to assess potential project risk occurrences.

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    81% (17)
  • D
    10% (2)