Which of the following describes the point in time when resources can be assigned to scheduled tasks?

The correct answer is C. When the work breakdown structure (WBS) is decomposed into work packages. See the full explanation below for the reasoning.

Question

Which of the following describes the point in time when resources can be assigned to scheduled tasks?

Options

  • AWhen the project statement of work (SOW) has been created
  • BWhen the project deliverables have been defined
  • CWhen the work breakdown structure (WBS) is decomposed into work packages
  • DWhen the project WBS dictionary has been created

How the community answered

(48 responses)
  • A
    15% (7)
  • B
    2% (1)
  • C
    77% (37)
  • D
    6% (3)