JK0-017 · Question #397
Which of the following elements does a project charter contain?
The correct answer is A. A project scope statement. See the full explanation below for the reasoning.
Question
Which of the following elements does a project charter contain?
Options
- AA project scope statement
- BA change management template
- CA completed request for proposal (RFP)
- DA complete list of the key performance indicators (KPIs)
How the community answered
(45 responses)- A76% (34)
- B13% (6)
- C7% (3)
- D4% (2)