Which of the following elements does a project charter contain?

The correct answer is A. A project scope statement. See the full explanation below for the reasoning.

Question

Which of the following elements does a project charter contain?

Options

  • AA project scope statement
  • BA change management template
  • CA completed request for proposal (RFP)
  • DA complete list of the key performance indicators (KPIs)

How the community answered

(45 responses)
  • A
    76% (34)
  • B
    13% (6)
  • C
    7% (3)
  • D
    4% (2)