JK0-017 · Question #388
Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the…
The correct answer is D. Risk register. See the full explanation below for the reasoning.
Question
Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the following should the shared resource be documented?
Options
- AQuality management metrics
- BWork Breakdown Schedule (WBS)
- CScope statement
- DRisk register
How the community answered
(51 responses)- A10% (5)
- B6% (3)
- C4% (2)
- D80% (41)