JK0-017 · Question #387

A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?

The correct answer is B. Analyze the impact of the change. See the full explanation below for the reasoning.

Question

A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time?

Options

  • ALower the quality standards for the finished product.
  • BAnalyze the impact of the change.
  • CEliminate 10 percent of the projects resources.
  • DDocument the approved change request.

How the community answered

(20 responses)
  • A
    10% (2)
  • B
    80% (16)
  • C
    5% (1)
  • D
    5% (1)