CompTIA
JK0-017 · Question #389
Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this…
The correct answer is D. Risk transference. See the full explanation below for the reasoning.
Question
Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this situation?
Options
- ARisk avoidance
- BRisk mitigation
- CRisk acceptance
- DRisk transference
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C6% (2)
- D81% (25)
Community Discussion