JK0-017 · Question #35
Due to unforeseen schedule blowouts, the project manager is forced to compress the next set of activities in order to avoid affecting the project delivery date. Which of the following techniques can…
The correct answer is A. Fast tracking B. Crashing. See the full explanation below for the reasoning.
Question
Due to unforeseen schedule blowouts, the project manager is forced to compress the next set of activities in order to avoid affecting the project delivery date. Which of the following techniques can be used to help achieve this? (Select TWO).
Options
- AFast tracking
- BCrashing
- CDelaying
- DQuality control
- EScope reduction
How the community answered
(64 responses)- A81% (52)
- C11% (7)
- D5% (3)
- E3% (2)