Which of the following tasks is essential to update a critical production component prior to project delivery?

The correct answer is D. Initiate change control process. See the full explanation below for the reasoning.

Question

Which of the following tasks is essential to update a critical production component prior to project delivery?

Options

  • APerform post-change testing
  • BRelease project costs
  • CReceive vendor sign-off
  • DInitiate change control process

How the community answered

(38 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    11% (4)
  • D
    84% (32)