A specific deliverable is needed in order to meet a project requirement. Another project has already constructed this deliverable and there is a strategic push for re-usable, leveraged components to…

The correct answer is C. Plan to leverage the other project's deliverables, make a direct project cost savings and meet. See the full explanation below for the reasoning.

Question

A specific deliverable is needed in order to meet a project requirement. Another project has already constructed this deliverable and there is a strategic push for re-usable, leveraged components to be utilized. Which of the following actions should the project manager take?

Options

  • AIgnore the other project so as not to introduce inter-dependencies between projects as this could
  • BIdentify project dependency as a threat, update risk register and inform stakeholders so that a
  • CPlan to leverage the other project's deliverables, make a direct project cost savings and meet
  • DEscalate the issue to the project sponsor so that a project decision can be made so that the

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    10% (3)
  • C
    79% (23)