JK0-017 · Question #33

A key supplier has informed the project manager that there will be a two month delay to fulfill an order. Which component of the project plan is affected and which of the following actions should be…

The correct answer is A. Evaluate the project schedule and raise a project issue. See the full explanation below for the reasoning.

Question

A key supplier has informed the project manager that there will be a two month delay to fulfill an order. Which component of the project plan is affected and which of the following actions should be taken?

Options

  • AEvaluate the project schedule and raise a project issue.
  • BManage project quality and schedule a meeting.
  • CImplement approved changes by utilizing a change management form.
  • DManage scope and consider a project change request.

How the community answered

(28 responses)
  • A
    75% (21)
  • B
    7% (2)
  • C
    14% (4)
  • D
    4% (1)