Senior executives within a company have noticed an increasing number of projects failing to deliver to requirements. Which of the following project governance methods will help to meet this need?
The correct answer is A. Phase gate approval. See the full explanation below for the reasoning.
Question
Senior executives within a company have noticed an increasing number of projects failing to deliver to requirements. Which of the following project governance methods will help to meet this need?
Options
- APhase gate approval
- BProject phase transition
- CISO standards compliance
- DAudit trail
How the community answered
(34 responses)- A82% (28)
- B9% (3)
- C3% (1)
- D6% (2)