The project manager is trying to determine what to present at a project kick-off meeting. Should a high-level project schedule be included?

The correct answer is D. Yes. High level project schedules are typically presented at a kick-off meeting. See the full explanation below for the reasoning.

Question

The project manager is trying to determine what to present at a project kick-off meeting. Should a high-level project schedule be included?

Options

  • AIt depends. Some stakeholders are not technical enough to understand them.
  • BNo. The project is likely to still be in the initiation phase which is too early for a project schedule.
  • CYes. Project schedules are required to ensure that stakeholders are bound to the scope.
  • DYes. High level project schedules are typically presented at a kick-off meeting.

How the community answered

(58 responses)
  • A
    12% (7)
  • B
    3% (2)
  • C
    7% (4)
  • D
    78% (45)