JK0-017 · Question #30

Within a corporation, project managers are assigned people based on defined roles and responsibilities. Project resources are temporarily provided to the project but still report the functional…

The correct answer is B. Matrix management. See the full explanation below for the reasoning.

Question

Within a corporation, project managers are assigned people based on defined roles and responsibilities. Project resources are temporarily provided to the project but still report the functional managers as well as the project manager. Which of the following styles of management is this also known as?

Options

  • AProjectized management
  • BMatrix management
  • CFunctional management
  • DSCRUM / agile

How the community answered

(44 responses)
  • A
    9% (4)
  • B
    75% (33)
  • C
    5% (2)
  • D
    11% (5)