JK0-017 · Question #348

A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change's effect on the project?

The correct answer is A. Performing an impact analysis. See the full explanation below for the reasoning.

Question

A stakeholder wants to add another requirement to the deliverable. Which of the following will the project manager do to determine the change's effect on the project?

Options

  • APerforming an impact analysis
  • BIdentifying a change
  • CCoordinating with stakeholders to select the course of action
  • DFilling out a change control

How the community answered

(47 responses)
  • A
    72% (34)
  • B
    4% (2)
  • C
    9% (4)
  • D
    15% (7)