Which of the following is the FIRST step in a proper change management procedure?
The correct answer is D. Identify a change. See the full explanation below for the reasoning.
Question
Which of the following is the FIRST step in a proper change management procedure?
Options
- ACoordinate with appropriate stakeholders
- BUpdate the project plan
- CPerform impact analysis
- DIdentify a change
How the community answered
(21 responses)- A5% (1)
- B5% (1)
- C14% (3)
- D76% (16)