A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?

The correct answer is C. WBS. See the full explanation below for the reasoning.

Question

A project team is ready to identify activities needed to accomplish the project. Which of the following needs to occur FIRST?

Options

  • APERT
  • BRBS
  • CWBS
  • DOBS

How the community answered

(46 responses)
  • A
    17% (8)
  • B
    4% (2)
  • C
    72% (33)
  • D
    7% (3)